Pioneer Power Centre
TERIC Power are the proud developers of the Pioneer Power Centre Project. The proposed project will consist of an up to 9.5 MW natural-gas-fired electricity generation facility, accompanied by an up to 16 MW / 32 MWh Battery Energy Storage System for an installed nameplate capacity of up to 25.5 MW.
- Stage Development
- Type Gas-Fired Power Gen / Battery Energy Storage
- BESS Size/Duration 16MW/32MWh
- Generator Size 9.5MW
- Total Installed Capacity 25.5MW
Project Location
This project is located near the town of Onaway AB
See more projectsProject Overview
TERIC Power Ltd. (TERIC) intends to apply to the Alberta Utilities Commission (AUC) to construct and operate an up to 9.5 MW natural-gas-fired electricity generation facility (generators), accompanied by an up to 16 MW / 32 MWh Battery Energy Storage System (BESS) on the NW and SW ¼ of Section 36, Township 54, Range 2, West of the 5th Meridian surface location, near the town of Onoway, Alberta. The project will be located on privately owned previously disturbed land.
The project will have a combined installed nameplate capacity of up to 25.5 MW. The BESS will be used to store electricity for discharge into the local distribution system as needed, while also providing on-demand reliability support to the Alberta Electric System Operator (“AESO”). The generators will be used to provide peaking power to the local distribution system during periods of high demand, grid instability, or renewable power intermittency.
Community Benefits
The project will generate municipal tax revenue that will contribute to the tax base for Lac Ste. Anne County while requiring minimal municipal services. During the construction phase, the project will provide local jobs for electricians, equipment operators, labourers, specialized trades, site managers and engineers.
Once operational, on-going site services such as project operators, electricians, and vegetation control jobs, will be required. Additionally, the procurement of materials and local support services such as accommodations and food services for workers, will be required during both the construction and operations phases.
Stakeholder Engagement
TERIC is committed to working with all stakeholders to keep them informed of our development activities. We pledge to listen to input and to address any concerns, directly consulting with the landowners, occupants, and the residents in the area. We welcome your feedback, so please contact a TERIC representative with any questions or comments regarding the Project.
Project Documents
Contact Us About This Project
Contact info@tericpower.com to request a copy of the project information package by mail or email, or to schedule a telephone consultation with a TERIC project representative.
Alternatively, please use the form below and a TERIC representative will reach out directly: